We are a team of professionals that has been operating in the IT and data center sectors for over 20 years, active on the European territory with various proven and successful experiences in digital technologies and data centers.<br />
<br />
We have been interested in the world of cryptocurrencies since some time and we believe that it will soon play an interesting – if not vital – role for the development of similar realities.
1) September 2017 – Idea to create a multi-activity data center (mining / hosting / housing / application development) powered with renewable energy to completely reduce energy costs;<br />
<br />
2) September/October 2017 – Market analysis and project feasibility;<br />
<br />
3) October/November 2017 – Analysis of the “best location” where to implement the project; project feasibility in relation to costs and tax system;<br />
<br />
4) November 2017 – Development of the auto-switch to automatically select the most profitable cryptocurrencies to be mined; beginning of the development of the “Online Service Marketplace Platform” app;<br />
<br />
5) November/December 2017 – Beginning of the development for the project entailing the realization of data center, wind farm and solar park;<br />
<br />
6) December 2017 – Beginning of the whitepaper creation;<br />
<br />
7) December 2017/January 2018 – Beginning of the final drafting for the wind farm construction in Tenerife;<br />
<br />
2018
8) January 2018 – Beginning of crowdsale planning and general marketing activities in general;<br />
<br />
9) January/February 2018 – End of the auto-switch development;<br />
<br />
10) February 2018 – Negotiations with D-Alix; other negotiations with Chinese companies for the hardware supply;<br />
<br />
11) February/March 2018 – Final project for the wind farm construction;<br />
<br />
12) March 2018 – Whitepaper completion and website creation;<br />
<br />
13) April/May 2018 – Marketing and communication;<br />
<br />
14) From 4 June 2018 to 1 May 2019 – Crowdsale;<br />
<br />
15) July 2018 – Opening of negotiations with major exchange<br />
<br />
2019
16) April 2019 – Company establishment in Tenerife;<br />
<br />
17) 2nd quarter of 2019 –Land purchase and beginning of the construction works for data center wind farm and solar park;<br />
<br />
18) 3rd quarter of 2019 – Realization of the solar park;<br />
<br />
19) 4th quarter of 2019 – Installation of the prefabricated shed; realization of the electric system; start of the wind farm works;<br />
<br />
2020
20) 1st and 2nd quarter of 2020 – Solar park testing; end of the wind farm works; testing and launch of the whole structure;<br />
<br />
21) 3rd and 4th quarter 2020 – Migration of mining systems to our data center;
Screenshots taken on 28 Nov 2018
Luca Puppi
CoFunder / General Manager at Hosting
Participates in a number of projects
Massimo Ferretti
Togacoin.com CoFunder and Legal Advisor
Participates in a number of projects
Sergio Livrieri
Togacoin.com CoFunder / General Manager at Hosting Giga.it
Participates in a number of projects
Slavomira Jobbagyova
Togacoin.com CoFounder and CEO of Inmediatamente WEB SL